Fluor
Learns costly EPC lessons
from Greater Gabbard
Long delays and heavy cost
overruns at the 504MW Greater Gabbard offshore wind project have taught an
“expensive lesson” to engineering, procurement and construction (EPC) giant
Fluor, and developers Scottish and Southern Energy (SSE) and RWE Npower
Renewables.
US engineering
giant Fluor Corporation says third quarter results will take a hit of $163m, or
$0.90 a share, because of estimated cost increases on the Greater Gabbard
Offshore Wind Project in the UK.
In a statement,
Fluor says its full-year earnings will now be between $2.20 and $2.50 a share,
versus an earlier estimate of $2.90 to $3.20 a share. It expects to release Q3
results by 4 November.
“During the
third quarter, the project experienced a variety of execution challenges,
including material and equipment delivery issues, primarily relating to the
installation of wind turbine generators and subsea cabling,” the company says
in a statement.
Fluor says it revised estimates to include
substantial costs for additional marine vessels and other subcontractor costs
associated with equipment installation, equipment repairs and the estimated
schedule impact which has been exacerbated by weather-related delays.
“The company
has taken a number of remedial actions to mitigate further cost escalation and
delays to the schedule,” it adds.
Fluor is the
main contractor for the 504MW Greater Gabbard scheme located 23km off the
Suffolk coast. Developer Scottish and Southern Energy is the
developer in the 50-50 joint venture with RWE.
In 2008, Fluor
was awarded a $1.8bn fixed price contract to construct the wind farm. To date,
all 140 monopiles and tower transition pieces have been installed and 53 of 140
wind turbine generators are in place.
Installation
and commissioning of the remaining wind turbine generators, subsea inter-array
cabling and grid substations are expected to continue through the latter part
of 2011. The overall project is expected to be completed in early 2012,
according to Fluor.
The project has
experienced a number of challenges since construction began in late 2008.
Through the second quarter of 2010, the company had recorded $202m in claim
revenue relating to costs incurred on a dispute with the joint venture
regarding specifications for monopiles and transition pieces required under the
contract, says Fluor.
Additional
costs arising from this dispute are expected to be incurred in future quarters.
Fluor continues to pursue claims for costs recoverable under the contract, it
says.
Richard A. Kessler (richard.kessler@rechargenews.com)
Godfrey Sayers 05/05/2011
Godfrey Sayers 05/05/2011
No comments:
Post a Comment